The Challenge
Expanding the capacity of the existing Sarasota Central County Water Treatment Facility while it continued to function.
We were also the on-call service for the county facility during hurricane Irma.
The Results
Doubled the capacity of the existing facility while it continued to operate. This project was an environmental win for the Sarasota area as it allowed the closure of an aging waste water plant on Siesta Key.
The Skills
The project doubled the capacity of the facility and consisted of installing and expansion of
Installed electrical, control and instrumentation wiring from new and existing MCCs, PLCs, and standby systems (generators).